Hello, we're running Project Server 2010 with Project Professional 2010 as well.
On our test server, I created an enterprise custom field: Entity - Task. Type - Text. No formula, no lookup table.
I added that field to one of our test projects in Project Professional and added values for each task. I saved the project and then published it without any issues.
I added that custom field to the view for Tasks and Timesheet but when I view either one, the field is there but there's no data. It's blank for every task.
When I reopen the project in Project Professional, the values are still there for that custom field and I can't understand why it's not populating in PWA.
Any help would be greatly appreciated!
Thanks,
Andre