Importing Custom Project Fields from Project Plan into PS List

$
0
0

I decided the best way to do a risk assessment was to create custom fields in the MS project plan for Risks, Triggers, probably, impact, mitigation etc.  I then learned that PS has a Risk Log with these variables.  It there anyway for me to continue my process and get these fields imported into the Risk List (even if I have to save offline in excel doc)?  I see you can "export" or open in acccess, but I don't see how this can help me.

Thank you in advance.

Lisa Chipetine, PMP