Can a zero duration task not be a milestone?

$
0
0

So we have a status report that shows milestones and some of our PMs go a little crazy with milestones so before they run the report they show the 'Milestone' field and turn some of their extraneous milestones to 'No'.

(Yes i could rewrite the report using a custom field to determine which milestones get added.)

The PMs in question have noticed that the 0 duration tasks that they toggled to 'no' have become 'yes' again without their actions.  Via testing I have not yet determined how this is happening.

So my question is can a 0 duration task ever not be a milestone permanently and under what conditions will the program flip the switch from 'no' to 'yes' for these tasks.