Tasks split using Resourse Usage change once published to PWA sever.
Issue
Once I save, publish and close project the resource time allocation is jumbled on reopening the plan.
Questions
- Does MS Project Professional 2013 and PWA allow saving and publishing of split tasks in project plans?
- Is there any setting that needs to be changed?
Background
Our reoccuring projects have 7 stages (therefore 7 "tasks" in ms project) are are completed in a windfall process.
Project Planning is completed at stage level, with mutiple (1-4) resources assigned to each stage. The resources time for each stage is inputted and updated in the resource usage view.
I assign resources to task and then update resource time allocation in resource usage. Resources are either booked for 3.5hrs or 7hrs.