Hello,
We currently have actuals locked down so that they can only be updated by a resource through PWA. We have a resource who erroneously added hours incorrectly and then left the account/company. How can I correct these hours in PWA and still keep the project schedule in Sync (and also have the hours appear correctly in reports)?
Can someone please point me to the process that accommodates this need while actuals are locked?
Thank you!
Randy