Hi,
I am facing issue relating to project schedule update. Once a resource submits the Task update and it is approved by the Project Owner it does not update the schedule immediately and in Project center old %age of completion is shown.
Secondly, the Schedule and Cost indicators are not showing up as well, it takes couple or mins sometimes hours to get indicators updated.
I have already changed the queue settings in the queue server to process 16 jobs in parallel.
Regards, Syed Faizan ur Rehman, CBPM®,PRINCE2®, MCTS