I have a unique request from my client. A group of resources would have assignments, lets say 10 users and their default assignment owner would be the project manager. We will open PWA to enter the task progress (My Tasks). Now if the project manager goes to PWA, he can see all the tasks assigned to his resources. However, if a task is assignment to multiple resources, the tasks is repeated for those 10 resources (which is correct as it is an resource assignment view). What he wants to have the task display on once for all of those resources and he can enter % complete at the task level.
Example: T1 has 100 hours and assigned to R1, R2, R3 and R4 (Their default assignment owner is M1)
When M1 goes to My Tasks view, he only want to see T1 once for all these resources, so he can update the % complete at the task level.
We can give Project Center access but in order to update the project's task, project needs to be checked out, which is nit an option as there are 15 PM using the same project plan and it would create a checkout/checkin hassle.
Is it doable? Please help