Hi,
When a Project Manager creates or edits a task that has no resources, they become the Assignment Owner for the "Unassigned" resource on this task. If they leave the company, they can't be deleted because they are Assignment Owners. However, the Assignment Owner field is disabled on these assignments (e.g. in the Resource Usage view). The only way I can see to solve the problem is to assign a resource to each affected task, and then delete the resource (and manually update the task to undo whatever changes may occur as a result). At this point, the user who is doing this "fixing" becomes the new Assignment Owner. Is there are way to update this Assignment Owner field that I am missing?
Thanks,
Erik
Erik RHS