I need several S-curve based on several baseline in project server 2010. for actual progress, what I do is saving data in a sharepoint list then creating chart( I appreciate if you guide me for better procuder) but I don't know how to have S-curve for Plan progress based on several baseline.I saw some weblogs that introduce VBA but because of some limmitations I can't use VBA
how can I have plan S-Curve?